Every PG&E bore that crosses a sewer or storm drain has to be proven clean on camera before PG&E signs off. Here's what the Cross Bore team looks for on gas and electric bores, what makes a video fail, and how Apex gets your job through it.
A cross bore happens when a new pipe or conduit installed by a trenchless method, like horizontal directional drilling, accidentally goes through another underground pipe instead of passing above or below it. The most common victim is a sewer lateral or storm drain. The new line can sit inside the sewer for years with nobody knowing, until the sewer backs up.
When a gas line runs through a sewer, a plumber clearing a "clog" with a cutting head or auger can cut straight into the gas line. Gas then travels through the sewer into the home. A 2002 cross bore incident in Minneapolis ended in a fire and explosion that destroyed two homes.
An electric conduit bored through a sewer is a hidden hazard too: it blocks flow, and a drain cleaning tool can damage the conduit and the cable inside. That's why PG&E checks crossings on electric bores as well, not just gas.
PG&E's own advice to plumbers: assume any sewer obstruction could be a cross bore. Stop work and call PG&E at 1-800-743-5000 before you clear it.
PG&E started its Cross Bore Safety Program after a risk review of its gas system, and it has since grown into one of the largest programs in the country, with hundreds of thousands of sewer camera inspections completed. On new construction, the program works like this:
The contractor's CCTV company runs a camera through every sewer main, lateral and storm drain the bore crosses, records the video, and fills out the PG&E Cross Bore Inspection Log (form TD-4632P-01-F02). PG&E's Cross Bore team then watches the video. They have to be 100% sure that every crossed line is intact and nothing was bored through it. If they can't see it, they can't clear it, and the job doesn't close out.
Each line crossed is listed with its manhole or house number, street, footage, the inspection date, the camera company's notes, and the method of installation. The log is marked as either a pre-construction or a post-construction inspection, and the PG&E PM number on the log has to match the job's construction drawing.
Both need to prove the bore didn't damage anything it crossed. Gas bores carry the most scrutiny because of the explosion risk. Here's what we see on our PG&E jobs:
A failed video doesn't mean the bore hit anything. It means the Cross Bore team couldn't see enough to be 100% sure it didn't. Until they can, the inspection stays open. These are the most common reasons:
A sewer with a sag or "belly" holds standing water, and the camera can't see the bottom of the pipe through it. The Cross Bore team can't clear what's underwater, so the owner's line has to be repaired and then re-cameraed before the job can pass.
Old sewer and storm lines are often full of mud, gravel or roots. If the camera can't get through, or the view is blocked, the video fails. The line has to be hydro-jetted or cleaned with a combo truck and then re-cameraed.
Some laterals can't be launched from the main because of a blockage or a size reduction. The camera crew then needs property access to a cleanout for a push camera from the house side.
A wrong PM number, missing manhole IDs, or a map that doesn't match the field can send a log back. Every line on the log has to match the drawing and the video.
Many sewer and storm lines camera clean on the first run. Some don't, and nobody can know which ones until the camera goes in. That's why cleaning and re-camera work is never built into an Apex proposal. It's priced only if and when it's actually needed.
Building cleaning and re-camera costs into every bid would mean charging every client for a problem most jobs never have. Keeping them as change orders keeps your base price honest. You only pay for cleaning, repair and re-camera on the lines that actually need it, and you approve the cost before we do the work.
On a recent PG&E electric service in the South Bay, Apex bored about 555 feet of 4" conduit along a city street, parallel to the sewer main and storm drain. The post-construction CCTV found a storm main packed with mud and debris and sewer laterals blocked with gravel, so those segments had to be cleaned and re-cameraed before the Cross Bore team could clear the job. Here are the map and log from that job, with the job site details removed.
We review the PG&E drawing, sewer and storm records, and locates before drilling, and plan the bore to clear every gravity line.
Crossing utilities are exposed so we can see depth and keep proper separation while drilling.
The drill head is tracked the whole way, and depth and footage are recorded for the as-built.
We coordinate the camera company to inspect every sewer and storm line the bore crossed.
If a line is blocked with mud, gravel or debris, or is holding water, we tell you right away and price the hydro jetting, repair and re-camera as a change order for your approval.
We check the log, map and PM number against the drawing before submitting, so the Cross Bore team can clear the job without sending it back.
This page is a general guide based on PG&E's public cross bore safety information and our own experience on PG&E jobs. Exact requirements can vary by project, and PG&E's inspectors and Cross Bore team have the final say. Learn more on PG&E's sewer cleaning safety page.